1B
|
Problem:
Appeals to BAR approvals and
LUPs are time and cost inefficient and the county incurs excessive costs for
frivolous appeals.
Solution:
(1) Revise appeals process
to occur after BAR preliminary approval rather than at final which allows an
appellant to express formal concerns earlier in the process. A “Preliminary
intent to file appeal” would be the method/form to appeal the BAR’s
preliminary approval. This might encourage/initiate a mediation process
prior to final review and might reduce planning commission appeals of BAR
decisions.
(2)
No appeal at LUP-stage if “measures of substantial conformity” determine no
validity of appeal.
(3)
Provide additional standards in ordinances to address problem areas (see
section 1C Solution 2)
(4)
For LUP projects that include architectural/ design considerations but do not
require BAR review, initiate a mailed noticing procedure (as described above)
in addition to posted noticing. If the project is appealed, and the appeal is
based on design issues, project would go to BAR to resolve issues prior to
proceeding to an appeal before the Planning Commission. Identify thresholds
for when LUP projects that include architectural/design considerations would
require mailed noticing.
|
Future
|
Board of Supervisors-
Ordinance
Amendments
|
Group #3:
Ordinance and Policies;
Streamlining
Appeals
Group #2: Permit Process Subcommittee; identifying
ministerial permit levels
|
Fewer number of appeals due to streamlined
process and addressing issues earlier in the application process
|
|
1C
|
Problem:
Community dissatisfied with design
standards applied to projects not required to undergo BAR review.
Solution:
(1) Update current design
standards in community plans and develop standards for those
areas/communities without any design standards.
(2) Identify
new thresholds for BAR review to address problem areas (e.g., floor to area
ratios, size of additions, daylight plane, and privacy issues) and
incorporate into community plans and design standards developed for other
communities.
|
Future
|
Board of
Supervisors—
design standards
and/or community plans
|
Group#3:
Ordinance and Policies;
Community plans
|
Updated design standards for community plans and
new design standards for communities without design standards
|
|
1D
|
Problem:
Public is unaware of how to
participate in/not knowledgeable about BAR process.
Solution: (1) Include a new section in BAR guidelines that
describes the public participation process.
(2)
Televise BAR meetings so public either in audience or at home is aware of BAR
deliberations.
(3)
Ensure BAR Chair solicits public participation for each agenda item, as necessary:
have BAR members use microphones so public can follow discussion of BAR
members.
(4)
Post the public participation section from BAR guidelines by the speaker slips/agendas
in hearing room.
(5)
Add brief information section on public process/participation to BAR agenda
so those reading an agenda are aware of how they can participate.
|
Future
|
Director
|
Group #1: Nature of the Interaction
|
Informed and efficient public participation in
BAR process
|
|
1E
|
Problem:
Architectural Review Committees’
(i.e., approved homeowner’s associations/community design organizations)
project pre-approvals may not always be included/considered in BAR
applications/review.
Solution:
(1) Include a check box for Architectural
Review Committee (ARC) on preliminary plan checklist (informs applicant about
applicable ARC) and in plan check (informs BAR as to whether ARC conditions
have been satisfied).
(2)
Ensure agendas are emailed to each ARC so they may follow
projects appearing before the BAR and be aware/take necessary action to
ensure that pre-approvals are being done.
(3)
Update all BAR materials to include list of ARCs with contact information
and review procedures.
(4)
Incorporate links to ARC standards in PIT computerized ordinance/database
effort.
(5)
Continue to allow approvals from the ARC and the BAR on a concurrent basis.
|
Future
|
Director
|
Group #1: Nature of the Interaction
Online Ordinance/ Database
Effort
|
Less conflict between Architectural Review Committees’
project pre-approvals and County approvals
|
|
1F
|
Problem:
BAR application/planning design
review process is inefficient, lacks consistency in interpretation of
information throughout the planning/design review process, and incomplete
applications hinder BAR/planning process.
Solution:
(1) BAR application/land
use application to provide clarity (i.e., to provide thresholds-like grading)
and be decision-tree based to expedite planning review. Application
completeness becomes responsibility of applicant.
(2)
Planning staff to provide at conceptual design review a preliminary plan
check to the BAR and applicant. This would give information on project
deficiencies (e.g. zoning inconsistencies, non-receipt of community
architectural review committee pre-approvals, etc), ensure information is
consistent throughout the planning (from planner to planner) and design
review process, and provide BAR with complete information about the project.
|
Future
|
Director
|
Group #1: Nature of the Interaction
|
More complete applications; more efficient review
process
|
|
2. Permit
Process Contact person(s): Laurel
Perez, Peter Lawson, Anne Coates, Petra Leyva
|
|
2A
|
Problem:
Applicant and planner
uncertainty as to permit complexity, unreasonable submittal requirements, and
excessive and unpredictable processing timeframes.
Solution:
Create a total of four permit
categories with application submittal requirements and processing timeframes
commensurate with the permit level (e.g., Basic, Level 1, Level 2, Level 3 –
see attached for more detailed description). Create application forms that
match permit levels.
|
|
|
Need permit types and submittal requirements to
be coordinated with the “Decision Tree” effort.
|
Monitor processing timeframes and P&D
requests for additional information for accountability and possible
adjustments.
|
|
2B
|
Problem:
Submittal requirements are not
commensurate with project and frequent Department requests for material,
plans or reports that are not necessary for project analysis.
Solution:
Create and publish a “Decision
Tree” that allows planners and applicants to determine their permit type and
the plans and reports necessary to process their application. Planners must
ask “what more can be gained from additional report or information, is it
critical?”
|
|
|
|
Consistent use of Decision Tree will result in a
more predictable and reasonable review.
|
|
2C
|
Problem:
Applicants unclear on what needs
to be submitted. P&D requests additional information on most
applications.
Solution:
Create and use a “Submittal
Checklist” that is completed by P&D front counter staff specific to the
project and used by applicant to prepare submittal. Signed by both parties
for accountability. Department adopts policy to not accept incomplete
applications.
|
|
|
Application requirements need to tie into the
“Decision Tree”.
|
Monitor the number of complete applications
submitted and those apps that are turned-away at in-take.
|
|
2D
|
Problem:
Unreasonable timeframes for
processing ministerial projects.
Solution:
Assign reasonable processing
timeframes for Basic, Level 1 and Level 2 projects. P&D to increase
accountability for processing timeframes. Reward planners who meet
timeframes.
|
|
|
|
Monitor and report on success and adjust process
or timeframes if necessary.
|
|
2E
|
Problem:
Inconsistent, inexperienced
direction provided at front counter.
Solution:
Assign experienced planners to
the front counter and create opportunity for advancement for planners who
work the front counter. Need strong supervision and front counter
management. Supervisor available to staff and public at all times.
|
|
|
|
Monitor success and poll applicants and planners
periodically for feedback.
|
|
2F
|
Problem: No on-line access to applications, application
status, property information and maps.
Solution:
Provide applications, property
information/maps and interdepartmental comments and application review status
on-line.
|
Pending
|
|
Online Ordinance/ Database
Effort
|
Mission
accomplished once this information is available on-line.
|
|
2G
|
Problem:
Applications submitted that are
inconsistent with policy, insufficient / inaccurate information.
Solution:
Encourage planner consultations
and pre-application meetings. Do not accept incomplete or inaccurate
applications. Advertise this “no tolerance” on incomplete applications to
applicants.
|
|
|
|
Monitor frequency of consults and poll applicants
and planners on success.
|
|
2H
|
Problem:
Planner consultations and
pre-applications can take one month or more to obtain.
Solution:
Department to place priority on
planner consultations. Provide processing incentives for applications that
have pre-applications or planner consultations (i.e., reduced processing
timeframe)?
|
|
|
|
Case assignment & initial call/ meeting
within one week.
|
|
2I
|
Problem:
Pubic noticing requirements
delay project processing.
Solution:
Require applicants to complete
the noticing requirements (labels, radius map, noticing affidavit) and submit
with all applications that require noticing.
|
|
|
|
Monitor and report on success.
|
|
2J
|
Problem:
Applicants that are turned away
at In-Take because they are missing an item must make a new appointment and
wait to submit.
Solution:
During the In-Take meeting, the
planner will use the application submittal checklist to identify the
additional required item(s) and sign the form allowing the applicant to
submit at the counter without an appointment once they have the additional
item(s).
|
|
|
|
|
|
3. Ag Coordination Contact
person(s): Anne Almy, Andy Caldwell, Lannie Stableford, Jeff Thomas
|
|
3A
|
Problem: Redundant Federal, State and local agency
reviews delay time-sensitive agricultural projects and drive up agricultural
production costs.
Solutions: Streamline agricultural permit processing;
integrate P&D’s permit process with NRCS and CRCD agency efforts. Enable
NRCS and/or CRCD to work as lead permit agencies with P&D acting in an
oversight capacity; revise P&D’s land development fee schedule to reflect
value of changed work effort.
|
Actively engaging in discussions with Natural
Resources Conservation Service (NRCS) and Cachuma Resources Conservation
District (CRCD).
Reviewing existing agricultural/grading permit
streamlining programs in Napa, SLO and Ventura.
|
Board of Supervisors
|
|
Inclusion of NRCS and CRCD biologists on the
County’s approved consultant list.
Coordinated development of rural area watershed
management plans, with joint NEPA/CEQA documents, public review and full
program buy in by the County, implementation by farmers, NRCS and CRCD.
|
|
3B
|
Problem: Agricultural expansion is confuted by competing
interests/policies.
Solutions: Promote agricultural expansion wherever
feasible, including within urban areas. Reconcile application of resource
protection policies, including wetland protection policies (consider
applicable definition), to (inland) lands under agricultural production (or
proposed for conversion to ag) with County goals to expand and intensify
agricultural production in rural areas.
|
Brainstorm
|
Board of Supervisors
|
|
No net loss of acres under cultivation, including
both open field and greenhouses, from 1/2004 levels with the ultimate goal of
expanded acreage devoted to cultivated agriculture.
County/Ag partnership in development & publication
of Implementation of Resource Protection Policies on Lands In or Proposed for
Agricultural Production policy paper.
|
|
3C
|
Problem: Urban interests are being imposed on rural
lands through community plan updates.
Solution: Outside of the south coast, limit community
plans to designated urban, established rural neighborhood and inner rural
areas. Develop watershed management plans for all rural areas outside of
community plan boundaries.
|
|
Board of Supervisors
|
Group #3, Ordinance and Policies
|
Community and area plan boundaries redrawn
consistent with recommended solution.
Development of rural area watershed management
plans and implementation in concert with NRCS and CRCD.
|
|
4. Case Assignment
Contact person(s): Laurel Perez, Anne
Coates, Petra Leyva
|
|
4A
|
Problem:
The current “rotational” case
assignment system results in overloaded planners receiving even more cases.
Solution:
Implement a case assignment
system that distributes cases to planners who have time to work on them (the
“Queue”).
|
|
|
|
Implement a pilot program and monitor its success
with applicants and P&D
|
|
4B
|
Problem:
Excessive delays for initial
planner contact with applicant.
Solution:
Commit to timeframe for initial
contact with applicant (within three weeks), with a meaningful feedback or
meeting with applicant within four weeks from submittal.
|
|
|
|
Supervise closely to confirm that applicants are
hearing from planners accordingly
|
|
4C
|
Problem:
No planner presence at
Conceptual BAR review.
Solution:
Need to further evaluate
possible solutions.
|
|
|
Need to coord. with the BAR group.
|
|
|
4D
|
Problem:
Subsequent applications for a
project are not always assigned to the same planner.
Solution:
Assign cases to the same planner
that previously worked on the project if the planner is still at P&D.
|
|
|
|
Supervise closely to confirm that this occurs
|
|
|
|
|
|
|
|
|
5. Interdepartmental Coordination
Contact person(s): Jessica Kinnehan
& Mary McCaffrey
|
|
5A
|
Problem: Lack of public information or education
regarding submittal requirements for land use and building permits.
Applicants want to be aware of what is needed for a complete submittal and if
their project is possible.
Solution: Implement Planning & Development website
containing user friendly online access to submittal requirements for various
projects, particular zoning requirements, building permit submittal
requirements, permit applications, etc., and to improve the permit process.
Provide minimal submittal requirements hand-outs for applicants. Provide
applicant’s with the option of having a pre-submittal meeting for Building
& Planning to review their plans for possible corrections, etc. A
check-off list would be provided to assist them in submitting a complete
project.
|
Process in the works.
|
|
|
Planning & Development website has been
modified and improved at present
|
|
5B
|
Problem:
Project requirements for
Planning & Development, County departments and related agencies (e.g.,
utility companies, etc.) for project permit process are not clear to
applicants. One department’s requirements may be detrimental to other
agencies’ requirements.
Solution:
Better and efficient
communication between Planning & Development departments, County
departments and related agencies to help determine submittal and project
requirements. Distribute plans to necessary departments or agencies as needed
for initial clearances for projects in timely manner. Provide the applicant
with a contact list (names & numbers) of which agency would require
clearances for their project.
|
This problem is being reviewed by our group
|
|
|
Communication with other County departments has
begun and it is recommended that departments coordinate with each other.
|
|
5C
|
Problem:
Applicants do not know whom to
contact regarding their project’s initial & final clearances and sometime
cannot contact the necessary agency to check status of their project
clearance or building permit status. Contractors would like to be able to
check the status of their building permit inspection and see if they passed
or if there are corrections.
Solution:
Coordinate with other County
departments and related agencies to provide an electronic clearance process
for final signoffs on Building projects. Provide public online accessibility
in regards to project permit status with County departments and related
agencies (the applicants can check their permit status online and confirm
other departments’ clearances.
Provide
a contact person for a particular department or agency if the public needs a
contact in regards to their project status.
Proposed
as a future service is online Building Permit Inspection status and possible
application for inspections.
|
Progress has begun, the electronic signoff
project is in the works and progressing well.
|
|
|
Presently, our group has attended a meeting
including Mike Zimmer and staff, County department heads and related agencies
on the electronic signoff process
|
|
6. Case Intake
Contact
person(s): Jack Boysen and Tom Frutchey
|
|
6A
|
Problem: Lack of public information or education
regarding submittal requirements for land use and building permits.
Applicants want to be aware of what is needed for a complete submittal and if
their project is possible.
Solution: A client-based approach toward applicants for
ministerial permits seems more appropriate than the current approach. To this
end, initial applicant contact should be directed to more senior supervisory
personnel. It is envisioned that application intakes would be at the
Supervising Planner and Senior Planner level and that this Case Manager
be the primary contact with the applicant throughout the permitting process.
The intake process would include a determination of applicant fees,
complexity of issues, and timeframe for completion.
|
Process in the works.
|
|
|
|
|
6B
|
Problem:
The Department
currently assigns a heavy caseload to each planner, so that: 1) a maximum
amount of time can be spent on case processing, with a small allowance for
downtime; and 2) the ebbs and flows of application submittals does not impact
staffing levels. In many ways, however, these high caseloads have the
opposite of the intended effects.
Solution:
Decreasing caseloads
will actually reduce turnaround times and increase throughput. In addition,
decreasing caseloads will have a major positive impact on morale. Instead of
discouraging downtime, the Department should encourage time spent
|